$A$ and $B$ can complete a piece of work in $15$ days and $10$ days respectively. They contracted to complete the work for $Rs. 30000$. The share of $A$ in the contracted money will be (in $Rs.$)

  • A
    $18000$
  • B
    $16500$
  • C
    $12500$
  • D
    $12000$

Explore More

Similar Questions

$A$ and $B$ can do a work in $12$ days. $B$ and $C$ can do the same work in $15$ days. $C$ and $A$ can do the same work in $20$ days. How much time will $A, B,$ and $C$ take to complete the same work together (in days)?

Difficult
View Solution

$A$ labourer can do a job in $36 \text{ hours}$. After $9 \text{ hours}$,he takes a break. What fraction of the job is yet to be done?

Sita takes twice as much time as Gita to complete a work and Rita does it in the same time as Sita and Gita together. If all three working together can finish the work in $6$ days,then the time taken by each of them to finish the work is (in days):

Difficult
View Solution

$A$ man,a woman,and a boy can together complete a piece of work in $3$ days. If a man alone can do it in $6$ days and a boy alone in $18$ days,how long will a woman alone take to complete the work? (in days)

$A$ does $\frac{2}{5}$ of a work in $9$ days. Then $B$ joined him and they together completed the remaining work in $6$ days. $B$ alone can finish the whole work in (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo