$A$ and $B$ can do a piece of work in $20$ days and $12$ days,respectively. $A$ started the work alone and then after $4$ days $B$ joined him until the completion of the work. How long did the work last? (in days)

  • A
    $10$
  • B
    $20$
  • C
    $15$
  • D
    $6$

Explore More

Similar Questions

$A$ worker can complete a piece of work in $50$ days. On the first day,he works alone. On the second day,one more person joins him,on the third day,one more person joins them,and this process continues until the work is completed. How many days are needed to complete the work?

$A$ can do a piece of work in $30$ days,$B$ in $50$ days,and $C$ in $40$ days. If $A$ is assisted by $B$ on one day and by $C$ on the next day alternately,the work will be completed in (in days):

Difficult
View Solution

$S, T$ and $U$ can complete a work in $40, 48$ and $60$ days respectively. They received $Rs. 10800$ to complete the work. They begin the work together,but $T$ left $2$ days before the completion of the work and $U$ left $5$ days before the completion of the work. $S$ completed the remaining work alone. What is the share of $S$ (in $Rs.$) from the total money?

Difficult
View Solution

$A$ alone would take $27 \, \text{days}$ more to complete the job than if both $A$ and $B$ worked together. If $B$ worked alone, he would take $3 \, \text{days}$ more to complete the job than $A$ and $B$ working together. What time would they take if both $A$ and $B$ worked together? (in $\text{days}$)

$5$ men can prepare $10$ toys in $6$ days working $6$ hours a day. Then,in how many days can $12$ men prepare $16$ toys working $8$ hours a day? (in days)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo