$A$ completes a piece of work in $4 \text{ days}$ and $B$ completes it in $6 \text{ days}$. If they both work on it together,then the number of days required to complete the same work is (in $\text{days}$):

  • A
    $2 \frac{2}{5}$
  • B
    $3 \frac{2}{5}$
  • C
    $3 \frac{5}{2}$
  • D
    $2 \frac{5}{2}$

Explore More

Similar Questions

$P$ can complete a work in $12$ days working $8$ hours a day. $Q$ can complete the same work in $8$ days working $10$ hours a day. If both $P$ and $Q$ work together,working $8$ hours a day,in how many days can they complete the work?

Difficult
View Solution

$A, B$ and $C$ do a job in $6$ days,$12$ days and $15$ days respectively. After $\frac{1}{8}$ of the work is completed,$C$ leaves the job. The rest of the work is done by $A$ and $B$ together. What is the time taken to finish the remaining work? (in days)

$P$,$Q$ and $R$ contracted to do a work for $Rs. 4200$. $P$ can do the work in $6$ days,$Q$ in $10$ days and $R$ in $12$ days. If they work together to do the work,what is the share of $R$ (in $Rs.$)?

Ram,Rajan,and Rangan can do a certain work in $6, 12,$ and $24$ days respectively. In what time will they altogether do it? (in days)

While working $7$ hours a day,$A$ alone can complete a piece of work in $6$ days and $B$ alone in $8$ days. In what time would they complete it together,working $8$ hours a day? (in days)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo