$P, Q$ and $R$ undertake to do a work for $Rs. 660$. $P$ and $Q$ together do $8/11$ of the work and the rest is done by $R$ alone. How much should $R$ get? (in $Rs.$)

  • A
    $200$
  • B
    $160$
  • C
    $180$
  • D
    $190$

Explore More

Similar Questions

$A$ works thrice as good as $B$ and is,therefore,able to finish a piece of work in $60 \text{ days}$ less than $B$. Find the time in which they can complete it,working together (in $\text{days}$).

Difficult
View Solution

$A$ can finish a work in $18$ days and $B$ can do the same work in half the time taken by $A$. Then,working together,what part of the same work can they finish in a day?

$A$ and $B$ complete a job in $12 \text{ days}$,while $A, B$,and $C$ can complete it in $8 \text{ days}$. $C$ alone will finish the job in (in $\text{days}$):

$P$ and $Q$ can do a piece of work in $30$ and $40$ days respectively. They began the work together,but $P$ left after some days and $Q$ finished the remaining work in $12$ days. After how many days did $P$ leave?

$A$ does half as much work as $B$ in $\frac{3}{4}$ of the time. If together they take $18 \text{ days}$ to complete a work,how much time shall $B$ take to do it alone? (in $\text{days}$)

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo