$A$ and $B$ together can do a piece of work in $10$ days. $A$ alone can do it in $30$ days. The time in which $B$ alone can do it is (in days):

  • A
    $10$
  • B
    $12$
  • C
    $15$
  • D
    $20$

Explore More

Similar Questions

$A$ and $B$ can do a job alone in $12 \text{ days}$ and $15 \text{ days}$ respectively. $A$ starts the work and after $6 \text{ days}$,$B$ also joins to finish the work together. For how many days did $B$ actually work on the job?

Shashi can do a piece of work in $20$ days. Tanya is $25\%$ more efficient than Shashi. The number of days taken by Tanya to do the same piece of work is

Four examiners can examine a certain number of answer papers in $10 \, \text{days}$ by working for $5 \, \text{hours}$ a $\text{day}$. For how many $\text{hours}$ in a $\text{day}$ would $2$ examiners have to work in order to examine twice the number of answer papers in $20 \, \text{days}$? (in $\text{hours}$)

Difficult
View Solution

$A$ can lay railway track between two given stations in $16 \, days$ and $B$ can do the same job in $12 \, days$. With the help of $C$,they did the job in $4 \, days$ only. Then $C$ alone can do the job in (in $days$)

$A$ does half as much work as $B$ in $three-fourths$ of the time. If together they take $18$ days to complete a work,how much time shall $B$ take to do it alone? (in days)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo