$A$ and $B$ can complete a piece of work in $8$ days,$B$ and $C$ can do it in $12$ days,and $C$ and $A$ can do it in $8$ days. In how many days can $A, B,$ and $C$ together complete the work?

  • A
    $4$
  • B
    $5$
  • C
    $6$
  • D
    $7$

Explore More

Similar Questions

$A$ carpenter can build a cupboard in $48 \, \text{hours}$. After $12 \, \text{hours}$, he takes a break. What fraction of the cupboard is yet to be built?

$250$ men can finish a work in $20 \, \text{days}$ working $5 \, \text{hours}$ a day. To finish the work within $10 \, \text{days}$ working $8 \, \text{hours}$ a day,the minimum number of men required is:

$A, B$ and $C$ do a job in $6$ days,$12$ days and $15$ days respectively. After $\frac{1}{8}$ of the work is completed,$C$ leaves the job. The rest of the work is done by $A$ and $B$ together. What is the time taken to finish the remaining work? (in days)

Nikita,Nishita,and Kavita can complete a work in $2 \frac{2}{3}$ days. If Nishita and Kavita can complete it in $4$ days,and Nishita alone can do it in $6$ days,then in how many days can Nikita and Nishita complete the work?

Subhash can copy $50$ pages in $10$ $h$,Subhash and Prakash can copy $300$ pages in $40$ $h$. In how much time can Prakash copy $30$ pages? (in $h$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo