$12$ men complete a work in $9$ days. After they have worked for $6$ days,$6$ more men join them. How many days will they take to complete the remaining work?

  • A
    $2$
  • B
    $3$
  • C
    $4$
  • D
    $5$

Explore More

Similar Questions

$A$ and $B$ can complete a piece of work in $45$ and $40$ days,respectively. They began the work together,but $A$ leaves after some days and $B$ completed the remaining work in $23$ days. After how many days did $A$ leave?

Heena can do a work in $20$ days,while Himani can do the same work in $25$ days. They started the work jointly. $A$ few days later,Mayuri also joined them,and thus all of them completed the whole work in $10$ days. All of them were paid a total of $Rs. 700$. What is the share of Mayuri (in $Rs.$)?

$A,$ $B,$ and $C$ have to type $506$ pages to finish an assignment. $A$ can type a page in $12$ minutes,$B$ in $15$ minutes,and $C$ in $24$ minutes. If they divide the task into three parts so that all three of them spend an equal amount of time typing,what is the number of pages that $B$ should type?

$A$ can do a work in $10 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $5 \text{ days}$,then the fraction of the work that is left is:

Difficult
View Solution

$A,$ $B,$ and $C$ can do a work separately in $16,$ $32,$ and $48$ days respectively. They started the work together,but $B$ left $8$ days before and $C$ left $6$ days before the completion of the work. In what time is the work finished? (in days)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo