$A$ and $B$ can complete a piece of work in $18$ days; $B$ and $C$ in $24$ days; $C$ and $A$ in $36$ days. $A$ alone can complete the work in (in days):

  • A
    $48$
  • B
    $56$
  • C
    $40$
  • D
    none of these

Explore More

Similar Questions

Bansal,Gupta,and Singhal together can complete a work in $4 \, \text{days}$. If Bansal and Gupta together can complete the work in $4 \frac{4}{5} \, \text{days}$,and Gupta and Singhal together can do it in $8 \, \text{days}$,then Gupta alone can complete the work in (in $\text{days}$):

Difficult
View Solution

How many $days$ will $1648$ persons take to construct a dam,if $721$ persons can build the same in $48$ days?

$A$ can do a piece of work in $30$ days,$B$ in $50$ days,and $C$ in $40$ days. If $A$ is assisted by $B$ on one day and by $C$ on the next day alternately,the work will be completed in (in days):

Difficult
View Solution

$4$ men and $6$ women together can complete a work in $8$ days,while $3$ men and $7$ women together can complete it in $10$ days. $20$ women working together will complete it in (in days):

$3$ men and $4$ boys can complete a certain work in $8$ days,while $4$ men and $4$ boys can complete the same work in $6$ days. Then $2$ men and $4$ boys will finish it in ........ days.

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo