$A$ contract is to be completed in $50 \text{ days}$ and $105 \text{ men}$ were set to work,each working $8 \text{ hours a day}$. After $25 \text{ days}$,$\frac{2}{5}$ of the work is finished. How many additional men must be employed so that the work may be completed on time,with each man now working $9 \text{ hours a day}$?

  • A
    $34$
  • B
    $36$
  • C
    $35$
  • D
    $37$

Explore More

Similar Questions

$A$ team of $30$ men is supposed to do a work in $38$ days. After $25$ days,$5$ more men were employed and the work was finished one day earlier. How many days would it have been delayed if $5$ more men were not employed? (in days)

If $3$ men or $6$ women can do a piece of work in $16$ days,in how many days can $12$ men and $8$ women do the same piece of work? (in days)

$A$ and $B$ together can complete a work in $12$ days. $A$ alone can complete it in $20$ days. If $B$ does the work only for half a day daily,then in how many days will $A$ and $B$ together complete the work?

If $4$ men or $8$ women can do a piece of work in $15$ days,in how many days can $6$ men and $12$ women do the same piece of work?

Four examiners can examine a certain number of answer papers in $10$ days by working for $5$ hours a day. For how many hours in a day would $2$ examiners have to work in order to examine twice the number of answer papers in $20$ days?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo