Machine $P$ can print one lakh books in $8$ hours,machine $Q$ can print the same number of books in $10$ hours,while machine $R$ can print them in $12$ hours. All the machines are started at $9.00$ a.m. while machine $P$ is closed at $11.00$ a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished?

  • A
    $11.30$ a.m.
  • B
    $12.00$ Noon
  • C
    $12.30$ p.m.
  • D
    $1.00$ p.m.

Explore More

Similar Questions

$A$ and $B$ complete a job in $12 \text{ days}$,while $A, B$,and $C$ can complete it in $8 \text{ days}$. $C$ alone will finish the job in (in $\text{days}$):

$A$ tyre has two punctures. The first puncture alone would have made the tyre flat in $9 \,minutes$ and the second alone would have done it in $6 \,minutes.$ If air leaks out at a constant rate,how long does it take both the punctures together to make it flat? (in $minutes$)

$A$ can complete a work in $m$ days and $B$ can complete it in $n$ days. How many days will it take to complete the work if both $A$ and $B$ work together?

$A$ certain number of men complete a work in $160\, days$. If there were $38\, men$ more, the work could be finished in $20\, days$ less. How many men were originally there?

$8$ children and $12$ men complete a certain piece of work in $9$ days. If each child takes twice the time taken by a man to finish the work,in how many days will $12$ men finish the same work?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo