$18$ women can complete a work in $12$ days and $12$ men can complete the same work in $9$ days. In how many days will $8$ men and $8$ women complete that work? (in days)

  • A
    $9$
  • B
    $6$
  • C
    $12$
  • D
    $8$

Explore More

Similar Questions

$A$ does $\frac{2}{5}$ of a work in $9$ days. Then $B$ joined him and they together completed the remaining work in $6$ days. $B$ alone can finish the whole work in (in days):

$A$ can do a work in $20 \, \text{days}$ and $B$ in $40 \, \text{days}$. If they work on it together for $5 \, \text{days}$, then the fraction of the work that is left is:

$A$ and $B$ complete a job in $12 \text{ days}$,while $A, B$,and $C$ can complete it in $8 \text{ days}$. $C$ alone will finish the job in (in $\text{days}$):

$4$ men and $6$ women together can complete a work in $8$ days,while $3$ men and $7$ women together can complete it in $10$ days. $20$ women working together will complete it in (in days):

$A$ does $\frac{1}{5}$ of a work in a $week$. $B$ finishes the same in a fortnight. $B$ starts the work and works only for $3$ days. Thereafter,$A$ completes the job. In how many days will $A$ finish the remaining work?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo