$A, B$ and $C$ can do a piece of work individually in $8, 12$ and $15$ days,respectively. $A$ and $B$ start working,but $A$ quits after working for $2$ days. After this,$C$ joins $B$ until the completion of the work. In how many days will the work be completed?

  • A
    $5 \frac{8}{9}$
  • B
    $4 \frac{6}{7}$
  • C
    $6 \frac{7}{13}$
  • D
    $3 \frac{3}{4}$

Explore More

Similar Questions

If $12$ men and $16$ boys can do a piece of work in $5 \, \text{days}$,and $13$ men and $24$ boys can do it in $4 \, \text{days}$,then the ratio of the daily work done by a man to that of a boy is:

$A$ and $B$ can complete a piece of work in $15$ days and $10$ days respectively. They contracted to complete the work for $Rs. 30000$. The share of $A$ in the contracted money will be (in $Rs.$)

$A$ and $B$ can do a work in $12$ days,$B$ and $C$ in $15$ days,and $C$ and $A$ in $20$ days. If $A, B,$ and $C$ work together,they will complete the work in (in days):

$A$ can complete a work in $10$ days,$B$ in $12$ days,and $C$ in $15$ days. All of them began the work together; but $A$ had to leave the work after $2$ days of the start and $B$ also left $3$ days before the completion of the work. How long did the work last? (in days)

Amit and Sujit together can complete a data entry assignment in $5$ days. Sujit's speed is $80\%$ of Amit's speed and the total key depressions in the assignment are $5,76,000$. What is Amit's speed in key depressions per hour if they work for $8$ hours a day?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo