$A$ and $B$ together can do a piece of work in $30$ days. $A$ having worked for $16$ days,$B$ finishes the remaining work alone in $44$ days. In how many days shall $B$ finish the whole work alone?

  • A
    $30$
  • B
    $40$
  • C
    $60$
  • D
    $70$

Explore More

Similar Questions

$3$ persons undertake to complete a piece of work for $Rs. 1,200$. The $first$ person can complete the work in $8$ days,the $second$ person in $12$ days,and the $third$ person in $16$ days. They complete the work with the help of a $fourth$ person in $3$ days. What does the $fourth$ person get? (in $Rs.$)

$2$ men alone or $3$ women alone can complete a piece of work in $4$ days. In how many days can $1$ woman and $1$ man together complete the same piece of work?

$4$ men and $6$ women together can complete a work in $8$ days,while $3$ men and $7$ women together can complete it in $10$ days. How many days will $20$ women working together take to complete the same work?

$A$ can do $\frac{1}{3}$ of a work in $5 \text{ days}$ and $B$ can do $\frac{2}{5}$ of the work in $10 \text{ days}$. In how many $\text{days}$ can both $A$ and $B$ together do the work?

$6$ men can complete a piece of work in $12$ days. $8$ women can complete the same piece of work in $18$ days,whereas $15$ children can complete the piece of work in $10$ days. $4$ men,$12$ women,and $20$ children work together for $2$ days. If only men were to complete the remaining work in $1$ day,how many men would be required?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo