$A$ and $B$ can together complete a task in $18$ hours. After $6$ hours, $A$ leaves. $B$ takes $36$ hours to finish the rest of the task. How many hours would $A$ have taken to do the task if he worked alone?

  • A
    $54$
  • B
    $45$
  • C
    $21$
  • D
    $27$

Explore More

Similar Questions

$P, Q$ and $R$ can do a piece of work in $60$ days,$100$ days and $80$ days respectively. They work together to finish the work and receive $Rs. 2256$. Then $P$ will get (in $Rs.$)

Difficult
View Solution

$A$ carpenter can build a cupboard in $48 \, \text{hours}$. After $12 \, \text{hours}$, he takes a break. What fraction of the cupboard is yet to be built?

$A$ can do a piece of work in $30 \text{ days}$ while $B$ can do it in $40 \text{ days}$. $A$ and $B$ working together can do it in (in $\text{days}$)

$5$ men can prepare $10$ toys in $6$ days working $6$ hours a day. Then,in how many days can $12$ men prepare $16$ toys working $8$ hours a day? (in days)

$A$ and $B$ can do a piece of work in $30$ days,while $B$ and $C$ can do the same work in $24$ days and $C$ and $A$ in $20$ days. They all work together for $10$ days when $B$ and $C$ leave. How many days more will $A$ take to finish the work?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo