$A$ can do a work in $12 \, days$. When he had worked for $3 \, days$,$B$ joined him. If they complete the work in $3$ more $days$,in how many $days$ can $B$ alone finish the work?

  • A
    $6$
  • B
    $12$
  • C
    $4$
  • D
    $8$

Explore More

Similar Questions

$A$ can do a piece of work in $8$ days. $A$ undertook it for $Rs. 320$. With the help of $B$,he finishes the work in $6$ days. $B$'s share is (in $Rs.$):

$A$ and $B$ can do a piece of work in $8$ days,$B$ and $C$ can do the same work in $12$ days,and $A, B,$ and $C$ together complete it in $6$ days. The number of days required to finish the work by $A$ and $C$ together is:

Difficult
View Solution

$A$ work can be completed by $P$ and $Q$ in $12$ days,$Q$ and $R$ in $15$ days,and $R$ and $P$ in $20$ days. In how many days can $P$ alone finish the work?

Difficult
View Solution

$A$ takes twice as much time as $B$ or thrice as much time as $C$ to finish a piece of work. Working together,they can finish the work in $2$ days. $B$ can do the work alone in (in days):

$A$ can complete a piece of work in $10$ days,while $B$ alone can complete it in $15$ days. They work together for $5$ days and the rest of the work is done by $C$ in $2$ days. If they receive $Rs. 450$ for the whole work,how should they divide the money? (in $Rs.$)

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo