Kim can do a work in $3 \, \text{days}$ while David can do the same work in $2 \, \text{days}$. Both of them finish the work together and get $Rs. 150$. What is the share of Kim? (in $Rs.$)

  • A
    $30$
  • B
    $60$
  • C
    $70$
  • D
    $75$

Explore More

Similar Questions

$A$ alone can do a piece of work in $6$ days and $B$ alone in $8$ days. $A$ and $B$ undertook to do it for $Rs. 3200$. With the help of $C$,they completed the work in $3$ days. How much is to be paid to $C$ (in $Rs.$)?

Difficult
View Solution

$A$ can do a certain work in the same time in which $B$ and $C$ together can do it. If $A$ and $B$ together could do it in $10 \text{ days}$ and $C$ alone in $50 \text{ days}$,then $B$ alone could do it in (in $\text{days}$):

Difficult
View Solution

$A$ certain number of men complete a work in $160\, days$. If there were $38\, men$ more, the work could be finished in $20\, days$ less. How many men were originally there?

$P$ and $Q$ together can do a job in $6$ days. $Q$ and $R$ can finish the same job in $60/7$ days. $P$ started the work and worked for $3$ days. $Q$ and $R$ continued for $6$ days. Then the difference of days in which $R$ and $P$ can complete the job is

Difficult
View Solution

$A, B$ and $C$ can do a piece of work individually in $8, 12$ and $15$ days,respectively. $A$ and $B$ start working,but $A$ quits after working for $2$ days. After this,$C$ joins $B$ until the completion of the work. In how many days will the work be completed?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo